Question:

Discuss about the Business Case Governance.

Answer:

Introduction

Business Case Governance

This section outlines the set of regulations, policies, functions, regulations, procedures, processes, and responsibility of the stakeholders that define the management and control of the proposed public transport project in Punjab.

Project Context, Requirements and Challenges

This project is aimed at a single purpose of closing the huge gap between the demand and supply of transport to the residents of Punjab state (Discover India, 2016, p. 39). In collaboration with the Federal and local government as well as other stakeholders in the transport industry, we are convinced that the proposed project with provide a sustainable solution to the problem. With an effective plan, we are certain to convince the government and other investors on the importance of investing in new buses to ease the transport congestion (Blakemore, 2015, p. 33).

The success of the ‘Smart City’ project would require the collaboration of the government by providing the funds for the implementation and management. Second, the general public would play a vital role by embracing the project (Mohani, 2014, p. 91). Air pollution by the carbon emitted from the congested states like Punjab do a lot of harm to the atmosphere. By accepting to use proposed bus project, many private car will be left at home hence reducing carbon emission (Verzuh, 2015, p. 111). Likewise, the traffic congestion would be reduced in the city. In short, successful implementation of the project would require interdisciplinary and responsive corporation among everyone. 

The main challenge faced is having the government’s approval of the project. It should be noted that in the previous, similar initiatives have failed with the government citing lack sufficient funds. While the government invested in some projects in the past, they were abandoned along the way (Project Management Institute, 2004, p. 67).

Objectives of Governance 

Project governance is a requirement which is demanded by the government, regulators and other stakeholders before a project has been accepted. It provides the project developer internal control methods while reassuring the financers that the money spent on the project can has been justified (Scott, 2016, p. 61).  An effective governance will benefit the project in the following ways. First, optimizing the success of the project. Second, avoiding common errors that are likely to arise. And third, motivating the staff by supporting better communication.

Project governance will be used to demonstrate the following issues:

  • Adopting of a life cycle that would allow the review and approval of the project viability.
  • Communicating and recording decisions arrived at during each stage of the project.
  • Establishment of clearly defined responsibilities, performance criteria and roles to manage the project (Office of Government Commerce, 2006, p. 77).
  • Developing a supportive and coherent relationship between the government, project developer and other stakeholders.
  • Ensure that the project case is supported by adequate information and data that will enable the stakeholders to make reliable and well-researched decisions (Office of Government Commerce, 2009, p. 12).
  • Ensure that all the stakeholders have been involved fully in all stages of project development, implementation, management and control. Governance will be used in fostering trust and confidence between the stakeholders.
  • Will help in deploying suitable, experienced and qualified people to ensure the fully implementation of the project (Project Management Institute, 2013 , p. 86).
  • Ensure that the project will add value to the residents of Punjab after its full implementation.

For the purpose of the implementation of the proposed transport project in Punjab state, our governance strategy focuses on:

  1. An agreed governance strategy that in formally accepted and cover joint authority and common decision making that effectively enable communication with the government, project sponsors, project developer, stakeholders and other third parties (Leach, 2006, p. 211);
  2. A strategy that recognizes the apportionment of reward and risk;
  3. A governance that acknowledges the relevance of the existing governances that had been used previously and clearly outlining their strengths and weaknesses;
  4. The strategy that will allow the stakeholders their performance as well as the success of the business during the implementation period.
  5. A strategy that would establishes a clear path for dispute resolution, independent review and agreed reporting procedures (Kendrick, 2004, p. 51).

To prove our commitment, board of the management, with a collaboration with the government and public representative have ensured that the project have been properly managed since its initialization.  The standards that have been set by the board will be applied to harmonize between the processes, programmes and other components of the project (Verzuh, 2015, p. 99).

Best Practice Governance Models

This project will use the Business Process Management (BPM) which is a set of processes and workflows that allows the development, implementation, execution, monitoring, and optimizing of a project. BPM allows the achievement of the optimum solution of the project within a sequence of activities (Leach, 2006, p. 98). It also encourage the completion of the project within a specified period The system was chosen because it will continuously encourage the stakeholders about their roles and responsibilities, indicating the completion status of their portion of work and the remaining part as well the due time that the project ought to be completed. Therefore, it is believed that each team member will perform more consistently and faster to accomplish the goal(s) of the project (Project Management Institute, 2004, p. 65).

The BPM governance model was chosen based on the following attributes;

  1. The model defines accountability and roles which includes a clear deployment if responsibilities. Each process with the project will be headed by a process manager.
  2. Defining the project standards and policies.
  3. The model defines the project goals and objectives at each stage. This would ensure that the each stage is conforming to the general goal of the project upon its completion.
  4. It ensures that the business-level requirement that have been set out represents the views of all the stakeholders.
  5. Can be used to outline the necessary changes in the project.
  6. It helps in defining an efficient flow of information between the stakeholders involved in the project.
  7. BPM also includes an ongoing action feature which is used;
  • Monitoring the project KPIs and progress
  • Monitoring risks
  • Locating process bottlenecks and obstacles
  • Controlling the allocation of resources for the project tasks.
  • Training process participants
  • Getting feedback from the public on the performance of the project after its

Business Case Governance

This section outlines the set of regulations, policies, functions, regulations, procedures, processes, and responsibility of the stakeholders that define the management and control of the proposed public transport project in Punjab.

Project Context, Requirements, and Challenges

This project is aimed at a single purpose of closing the huge gap between the demand and supply of transport to the residents of Punjab state (Discover India, 2016, p. 39). In collaboration with the Federal and local government as well as other stakeholders in the transport industry, we are convinced that the proposed project with providing a sustainable solution to the problem. With an effective plan, we are confident to convince the government and other investors on the importance of investing in new buses to ease the transport congestion (Blakemore, 2015, p. 33).

The success of the ‘Smart City' project would require the collaboration of the government by providing the funds for the implementation and management. Second, the general public would play a vital role by embracing the project (Mohani, 2014, p. 91). Air pollution by the carbon emitted from the congested states like Punjab does a lot of harm to the atmosphere. By accepting to use proposed bus project, many private cars will be left at home hence reducing carbon emission (Verzuh, 2015, p. 111). Likewise, the traffic congestion would be reduced in the city. In short, successful implementation of the project would require interdisciplinary and responsive corporation among everyone. 

The primary challenge faced is having the government's approval of the project. It should be noted that in the previous, similar initiatives have failed with the government citing lack sufficient funds. While the government invested in some projects in the past, they were abandoned along the way (Project Management Institute, 2004, p. 67).

Objectives of Governance

Project governance is a requirement which is demanded by the government, regulators, and other stakeholders before a project have been accepted. It provides the project developer internal control methods while reassuring the financiers that the money spent on the project can have been justified (Scott, 2016, p. 61).  An effective governance will benefit the project in the following ways. First, optimizing the success of the project. Second, avoiding common errors that are likely to arise. And third, motivating the staff by supporting better communication.

Project governance will be used to demonstrate the following issues:

  • Adopting of a life cycle that would allow the review and approval of the project viability.
  • Communicating and recording decisions arrived at during each stage of the project.
  • Establishment of clearly defined responsibilities, performance criteria, and roles to manage the project (Office of Government Commerce, 2006, p. 77).
  • Developing a supportive and coherent relationship between the government, project developer, and other stakeholders.
  • Ensure that the project case is supported by adequate information and data that will enable the stakeholders to make reliable and well-researched decisions (Office of Government Commerce, 2009, p. 12).
  • Ensure that all the stakeholders have been involved fully in all stages of project development, implementation, management, and control. Governance will be used in fostering trust and confidence between the stakeholders.
  • Will help in deploying suitable, experienced and qualified people to ensure the full implementation of the project (Project Management Institute, 2013, p. 86).
  • Ensure that the project will add value to the residents of Punjab after its full implementation.

For the purpose of the implementation of the proposed transport project in Punjab state, our governance strategy focuses on:

  • An agreed governance strategy that is formally accepted and cover joint authority and common decision making that effectively enable communication with the government, project sponsors, project developer, stakeholders and other third parties (Leach, 2006, p. 211);
  • A strategy that recognizes the apportionment of reward and risk;
  • A governance that acknowledges the relevance of the existing governances that had been used previously and clearly outlining their strengths and weaknesses;
  • The strategy that will allow the stakeholders their performance as well as the success of the business during the implementation period.
  • A strategy that would establish a clear path for dispute resolution, independent review and agreed to report procedures (Kendrick, 2004, p. 51).
  • To prove our commitment, the board of the management, with a collaboration with the government and public representative have ensured that the project has been properly managed since its initialization. The standards that have been set by the board will be applied to harmonize between the processes, programs and other components of the project (Verzuh, 2015, p. 99). 

Best Practice Governance Models

This project will use the Business Process Management (BPM) which is a set of processes and workflows that allow the development, implementation, execution, monitoring, and optimizing of a project. BPM allows the achievement of the optimum solution for the project within a sequence of activities (Leach, 2006, p. 98). It also encourages the completion of the project within a specified period. The system was chosen because it will continuously encourage the stakeholders about their roles and responsibilities, indicating the completion status of their portion of work and the remaining part as well the due time that the project ought to be completed. Therefore, it is believed that each team member will perform more consistently and faster to accomplish the goal(s) of the project (Project Management Institute, 2004, p. 65).

The BPM governance model was chosen based on the following attributes;

  1. The model defines accountability and roles which include a clear deployment if responsibilities. Each process with the project will be headed by a process manager.
  2. Defining the project standards and policies.
  3. The model defines the project goals and objectives at each stage. This would ensure that the each stage is conforming to the general goal of the project upon its completion.
  4. It ensures that the business-level requirement that has been set out represents the views of all the stakeholders.
  5. Can be used to outline the necessary changes in the project.
  6. It helps in defining an efficient flow of information between the stakeholders involved in the project.
  7. BPM also includes an ongoing action feature which is used;
  8. Monitoring the project KPIs and progress
  9. Monitoring risks
  10. Locating process bottlenecks and obstacles
  11. Controlling the allocation of resources for the project tasks.
  12. Training process participants
  13. Getting feedback from the public on the performance of the project after its implementation.

High level WBS 

Proposed Transport System in Punjab

WBS #

Task

Description of Task

Work Products

Owners

Est. Level of Effort

1

PLANNING

 Management of all tasks and activities

 

 

 

1.1

Plan and Supervise

Observing that all the activities and tasks are conducted according to the plan and Business Process Management model.

 Roll-up Task

Project Manager in collaboration with the government and public representatives

6 months

1.1.1

Create Plan

Development of WBS, Business process management, work package identification, schedule formulation, resource estimation, and staffing projection.

Developing a detailed project plan which highlights all the key tasks, resources, milestones, duration and dependencies.

WBS,

BPM model and the project plan

Project Manager

2 months

1.1.2

Creating the Budget

Developing and documenting the estimated project budget on the basis of established plan and needed and required resources.

ITPR

Project Manager,

Project Sponsors (the government),

The Project team

2 weeks

1.1.3

Disbursement  and budget reconciliation

Developing budget disbursement process which comprises of acceptance and approval forms.

Deliverable Purchase Orders, Products

Acceptance Form

The Federal government

One Week

1.1.4

Coordinating the  Activities

Planning of continuous planning and execution tasks for the project that comprise of  weekly meetings

Meeting Minutes

Project Manager,

One Year

Project Timeline 

TASK

Responsibility

Time of completion

PLANNING

The entire project planning Team

3 years

Plan and Supervise

Project Manager in collaboration with the government and public representatives

6 months

Create Plan

Project Manager

2 months

Creating the Budget

Project Manager,

Project Sponsors (the government).

The Project team

2 weeks

Disbursement  and budget reconciliation

The Federal government

Within a span of 2 years

Coordinating the  Activities

Project Manager

One Year

Execution

Project Manager

One year

Evaluation

Project manager

At the end of the project

Key success Factors

The main objective of the project is to create sustainably and environment-friendly public transport system that will decongest Punjab state. The success of the project is aimed at improving economic efficiency because products and services will be delivered timely to the destinations.

Project Plans

The project plan is as discussed in the paper as stated above.

Stakeholder Management Plan

The main stakeholders in the proposed project plan are the project manager, the team, the government representative and the general public within the Punjab state. Through series of meetings and consultations, the stakeholders will come up with a comprehensive management plan the will promote interdisciplinary communication (Kerzner, 2005, p. 76). The management plan will also outline a dispute resolution method to be used in handling conflicts that are likely to occur.

We seek a mutual relationship that will convert different interests from different groups into a mutual agenda which will solve the transport problem facing the Punjab state.

References List

Blakemore, S., 2015. Project Management for the Unofficial Project Manager: A FranklinCovey Title. London : BenBella Books .

Discover India, 2016. Transportation In Punjab. [Online]
Available at: http://www.discoveredindia.com/punjab/transportation-in-punjab/
[Accessed 18 August 2016].

Kendrick, T., 2004. The Project Management Tool Kit: 100 Tips and Techniques for Getting the Job Done Right. NEW yORK: AMACOM/American Management Association .

Kerzner, H. R., 2005. Project Management: A Systems Approach To Planning, Scheduling, And Controlling. New Jersey: Wiley.

Leach, L. P., 2006. Lean Project Management: Eight Principles for Success. London: Booksurge Publishing.

Mohani, V., 2014. Punjab's fairy tale public transport projects. [Online]
Available at: http://timesofindia.indiatimes.com/city/chandigarh/Punjabs-fairy-tale-public-transport-projects/articleshow/39325711.cms
[Accessed 18 August 2016].

Office of Government Commerce, 2006. Business benefits through programme and project management. Chicago: Stationery Office.

Office of Government Commerce, 2009. Managing Successful Projects with PRINCE2. Chicago: Office of Government Commerce .

Project Management Institute, 2004. A Guide to the Project Management Body of Knowledge: PMBOK Guide. New York: Project Management Institute.

Project Management Institute, 2013 . A Guide to the Project Management Body of Knowledge (PMBOK® Guide)–Fifth Edition. 5th ed. Chocago: Project Management Institute.

Scott, D. J., 2016. Project Management: A Quick Start Beginner's Guide For The Serious Project Manager To Managing Any Project Easily. New Jersey: CreateSpace Independent Publishing Platform .

Verzuh, E., 2015. The Fast Forward MBA in Project Management. 5 edition ed. New York: Wiley.

 

MyAssignmenthelp.co.uk has emerged as the one-stop solution for all students who are in search of professional assignment help. We not only help students in producing impeccable thesis papers but also provide complete thesis writing help starting from the selection of topics, researching the topics, structuring the paper and finally writing it. So no matter what problem restrains students, our thesis writing services will always be the perfect answer for students.

Why Student Prefer Us ?
Top quality papers

We do not compromise when it comes to maintaining high quality that our customers expect from us. Our quality assurance team keeps an eye on this matter.

100% affordable

We are the only company in UK which offers qualitative and custom assignment writing services at low prices. Our charges will not burn your pocket.

Timely delivery

We never delay to deliver the assignments. We are very particular about this. We assure that you will receive your paper on the promised date.

Round the clock support

We assure 24/7 live support. Our customer care executives remain always online. You can call us anytime. We will resolve your issues as early as possible.

Privacy guaranteed

We assure 100% confidentiality of all your personal details. We will not share your information. You can visit our privacy policy page for more details.

Upload your Assignment and improve Your Grade

Boost Grades