Introduction
Project management is considered as one of the methodological and semantic approach for utilizing the process, methods, knowledge, and skills for achieving the goal of the project within given resources. In this particular report, the project scope is developed for a ‘company retreat plan for 3 days and 2 nights at Batam, Indonesia’.
The project deals with developing and conducting a retreat company plan for its 20 customers and 25 employees on 13th September 2016. The members of the retreat program will leave on 13th September, Tuesday morning from Malaysia and return on 15th September, Thursday Night. The project has a budget of $40,000.
The scope of the project involves the determining the project goals, tasks, resource allocations. The six check items of the project scope are discussed below-
The objective of the ‘company retreat plan' is given below-
The deliverables of the project are usually defined as the task or requirements need to meet the project objectives and goals.
Deliverables | Data |
Communication Planning | Wed 8/10/16 |
Transportation | Thu 8/25/16 |
Activities | Tue 8/30/16 |
Food and Drinks | Mon 9/5/16 |
Execution Phase | Mon 9/12/16 |
Project Milestones are defined as the vital tasks and steps required to complete the execution of the project on time.
Task Name | Duration | Start | Finish |
Company retreat plans To Batam | 27 days | Wed 8/10/16 | Thu 9/15/16 |
start project | 0 days | Wed 8/10/16 | Wed 8/10/16 |
Communication Planning | 11 days | Wed 8/10/16 | Wed 8/24/16 |
Brainstorm for Ideas | 2 days | Wed 8/10/16 | Thu 8/11/16 |
select Venue | 2 days | Fri 8/12/16 | Mon 8/15/16 |
Select location for stay | 1 day | Tue 8/16/16 | Tue 8/16/16 |
Book Stay Location | 1 day | Wed 8/17/16 | Wed 8/17/16 |
Create invitation list | 2 days | Thu 8/18/16 | Fri 8/19/16 |
Send RSVP | 2 days | Mon 8/22/16 | Tue 8/23/16 |
Develop the timings of the Programs | 1 day | Wed 8/24/16 | Wed 8/24/16 |
Transportation | 3 days | Thu 8/25/16 | Mon 8/29/16 |
Brainstorm on transport idea | 1 day | Thu 8/25/16 | Thu 8/25/16 |
Select Air transport Idea | 1 day | Fri 8/26/16 | Fri 8/26/16 |
Book air tickets | 1 day | Mon 8/29/16 | Mon 8/29/16 |
Activities | 4 days | Tue 8/30/16 | Fri 9/2/16 |
Plan activity list | 2 days | Tue 8/30/16 | Wed 8/31/16 |
Plan Meeting Activity | 1 day | Thu 9/1/16 | Thu 9/1/16 |
Book Activity Area | 1 day | Fri 9/2/16 | Fri 9/2/16 |
Food and Drinks | 6 days | Mon 9/5/16 | Mon 9/12/16 |
list the dietary requirements | 1 day | Mon 9/5/16 | Mon 9/5/16 |
Inform the hotels about the requirement | 1 day | Tue 9/6/16 | Tue 9/6/16 |
select and confirm menu | 2 days | Wed 9/7/16 | Thu 9/8/16 |
Book food and drink packages | 2 days | Fri 9/9/16 | Mon 9/12/16 |
Execution Phase | 3 days | Mon 9/12/16 | Thu 9/15/16 |
Reach the destination on time | 0 days | Mon 9/12/16 | Mon 9/12/16 |
3 days, 2 nights stay | 3 days | Tue 9/13/16 | Thu 9/15/16 |
Take customer review | 0 days | Thu 9/15/16 | Thu 9/15/16 |
Return to Malaysia | 0 days | Thu 9/15/16 | Thu 9/15/16 |
Technical requirements: Not Applicable
Non-Technical Requirements: Financial Budget;
Human Resource;
The project excludes the following-
William Jones, Alexander Smith, and others.
Project Priority is a management tool for balancing between the performance, cost and time of the project.
Accept: The Accept criterion is defined as the measure up to what Performance, Cost and Time of the project are tolerable.
Enhance: The Enhance parameter defines which of the Performance, Cost and Time of the project can be optimized for enhancing the project.
Constraint: The Constrain parameter defines the elements in the project needs to remain constraint throughout the project.
| Performance | Cost | Time |
Accept |
|
|
|
Enhance |
|
|
|
Constraint |
|
|
|
The Priority Project matrix efficiently shows that cost of the project is borne by the company. Thus it needs to be feasible to conduct the project. The time provided for the project needs to remain constant for conducting the retreat plan to Batan. This is essential because, the booking of the venue, food and lodging are done before hand. Change in the timings of the project can result in the cancellation of the entire retreat plan. The performance of the project needs to be the constraint as it has the potential to build company's reputation.
Task Name | Cost |
Company Retreat Plan | $40,000.00 |
Communication Planning | $10,000.00 |
Transportation | $10,000.00 |
Activities | $5,000.00 |
Food and Drinks | $10,000.00 |
Execution Phase | $5,000.00 |
Table 1: Cost Estimation of the Retreat Plan
(Source: Created by Author in MS Project)
Bibliography
Alotaibi, A. B., & Mafimisebi, O. P. (2016). Project Management Practice: Redefining Theoretical Challenges in the 21st Century. Project Management, 7(1).
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Chia, R. (2013). Paradigms and perspectives in organizational project management research: implications for knowledge creation. Novel Approaches to Organizational Project Management Research: Translational and Transformational. Copenhagen Business School Press, Copenhagen, 33-55.
Crawford, J. K. (2014). Project management maturity model. CRC Press.
Heagney, J. (2012). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Kerzner, H. R. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.